Assessment Year | 1997 |
---|---|
Principal Product | Speciality auto tools |
NAICS |
n/a
|
SIC | 3423: Hand and Edge Tools, Except Machine Tools and Handsaws |
Sales Range | $5 M to 10M |
# of Employees | 50 |
Plant Area |
34,000
ft2
|
Annual Production | 3,500,000
pieces
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $15,734 | 329,132 |
kWh
|
$0.048 |
Electricity Demand | $3,240 | 846 |
kW-mo/yr
|
$3.83 |
Electricity Fees | $3,819 | - |
|
- |
Natural Gas | $2,716 | 421 |
MMBtu
|
$6.45 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $25,695 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $12,616 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $699 | $219 |
$472
9,965
kWh
|
$227
-
kW-mo/yr
|
- | - | - | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $999 | $200 |
$674
14,068
kWh
|
$325
-
kW-mo/yr
|
- | - | - | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $90 | $250 |
$61
1,172
kWh
|
$29
-
kW-mo/yr
|
- | - | - | - | - | |
04 | 2.7243: Improve air circulation with destratification fans / other methods | $398 | $1,998 |
$(-63.0)
(-1,465)
kWh
|
$(-30.0)
-
kW-mo/yr
|
$491
-
MMBtu
|
- | - | - | - | |
05 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $1,503 | - | - | - | - | - |
$1,503
-
lb
|
- | - | |
06 | 3.1191: Change procedures / equipment / operating conditions | $462 | $355 | - | - | - |
$32
-
gal
|
- | $80 | $350 | |
07 | 4.112: Replace old machine with new automatic multi-station tool | $7,488 | $15,000 | - | - | - | - | - | $7,488 | - | |
08 | 4.112: Replace old machine with new automatic multi-station tool | $12,681 | $50,000 |
$(-35.0)
(-586)
kWh
|
$(-84.0)
-
kW-mo/yr
|
- | - | - | $12,800 | - | |
09 | 4.432: Cross-train personnel to avoid lost time | $1,375 | $2,259 | - | - | - | - | - | $1,375 | - | |
TOTAL RECOMMENDED | $25,695 | $70,281 |
$1,109
23,154
kWh
|
$467
-
kW-mo/yr
|
$491
-
MMBtu
|
$32
-
gal
|
$1,503
-
lb
|
$21,743 | $350 | ||
TOTAL IMPLEMENTED | $12,616 | $18,283 |
$1,207
25,205
kWh
|
$581
-
kW-mo/yr
|
- |
$32
-
gal
|
$1,503
-
lb
|
$8,943 | $350 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs