ITAC Assessment: NC0107
ITAC logo
ITAC Assessment: NC0107
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Lawn mowers
NAICS
n/a
SIC 3524: Lawn and Garden Tractors and Home Lawn and Garden Equipment
Sales Range $50
M
to 100
M
# of Employees 289
Plant Area 127,600
ft2
Annual Production 201,638
pieces
Production Hrs. Annual 6,000
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $409,889 9,958,968
kWh
Electricity Demand $90,840 28,566
kW-mo/yr
Electricity Fees $17,263 -
Natural Gas $178,194 42,220
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $109,667 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $22,969

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $287 $420 $196
4,689
kWh
$91
-
kW-mo/yr
- - - -
02 2.4133: Use most efficient type of electric motors $1,452 $1,356 $1,258
30,481
kWh
$194
-
kW-mo/yr
- - - -
03 2.4239: Eliminate or reduce compressed air usage $242 $280 $195
4,689
kWh
$47
-
kW-mo/yr
- - - -
04 2.4239: Eliminate or reduce compressed air usage $69,557 $9,600 $60,246
1,463,658
kWh
$9,311
-
kW-mo/yr
- - - -
05 3.5315: Lease / purchase baler; sell cardboard to recycler $38 $100 - - - - $38
-
lb
-
06 3.3125: Use distillation, evaporation to remove contaminants $21,230 $15,000 $(-1,810.0)
(-125,733)
kWh
- $23,040
-
gal
- - -
07 3.1121: Use more efficient adhesive applicators $16,861 $2,000 - - - $37,111
-
gal
- $(-20,250.0)
TOTAL RECOMMENDED $109,667 $28,756 $60,085
1,377,784
kWh
$9,643
-
kW-mo/yr
$23,040
-
gal
$37,111
-
gal
$38
-
lb
$(-20,250.0)
TOTAL IMPLEMENTED $22,969 $16,776 $(-356.0)
(-90,563)
kWh
$285
-
kW-mo/yr
$23,040
-
gal
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs