ITAC Assessment: NC0101
ITAC logo
ITAC Assessment: NC0101
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Bedspreads
NAICS
n/a
SIC 2392: House furnishing, Except Curtains and Draperies
Sales Range $5
M
to 10
M
# of Employees 140
Plant Area 54,000
ft2
Annual Production 280,000
pieces
Production Hrs. Annual 4,000
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $59,628 1,262,603
kWh
Electricity Demand $24,817 5,075
kW-mo/yr
Electricity Fees $4,065 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $6,048 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,226

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
01 2.7111: Reduce illumination to minimum necessary levels $1,822 $800 $1,390
29,308
kWh
$432
-
kW-mo/yr
-
02 2.4133: Use most efficient type of electric motors $387 $422 $296
6,155
kWh
$91
-
kW-mo/yr
-
03 2.7131: Add area lighting switches $1,162 $750 $715
15,240
kWh
$447
-
kW-mo/yr
-
04 2.7243: Improve air circulation with destratification fans / other methods $625 $100 $473
9,965
kWh
$152
-
kW-mo/yr
-
05 3.1192: Reduce scrap production $2,052 - - - $2,052
-
lb
TOTAL RECOMMENDED $6,048 $2,072 $2,874
60,668
kWh
$1,122
-
kW-mo/yr
$2,052
-
lb
TOTAL IMPLEMENTED $4,226 $1,272 $1,484
31,360
kWh
$690
-
kW-mo/yr
$2,052
-
lb
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs