Assessment Year | 1996 |
---|---|
Principal Product | Wood veneer |
NAICS |
n/a
|
SIC | 2435: Hardwood Veneer and Plywood |
Sales Range | $10 M to 50M |
# of Employees | 125 |
Plant Area |
75,000
ft2
|
Annual Production | 30,000
thousand feet
|
Production Hrs. Annual | 2,750
hrs
|
Location (State) | South Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $59,605 | 1,654,162 |
kWh
|
$0.036 |
Electricity Demand | $48,048 | 5,736 |
kW-mo/yr
|
$8.38 |
Electricity Fees | $4,456 | - |
|
- |
Natural Gas | $56,288 | 15,341 |
MMBtu
|
$3.67 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $73,161 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $72,940 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #1 Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $778 | $1,676 |
$360
10,844
kWh
|
$418
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,187 | $5,250 |
$563
16,706
kWh
|
$624
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.4133: Use most efficient type of electric motors | $301 | $352 |
$143
4,396
kWh
|
$158
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $221 | $22 |
$105
3,224
kWh
|
$116
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.2136: Install / repair insulation on steam lines | $869 | $2,312 | - | - |
$869
-
MMBtu
|
- | - | - | |
06 | 2.1331: Burn a less expensive grade of fuel | $60,860 | $15,000 |
$34
879
kWh
|
$26
-
kW-mo/yr
|
$30,800
-
MMBtu
|
- | - | $30,000 | |
07 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $5,045 | $140,000 | - | - | - |
$(-955.0)
-
MMBtu
|
$6,000
-
lb
|
- | |
08 | 3.5316: Contract a wood pallet recycling company | $3,900 | $100 | - | - | - | - |
$3,900
-
lb
|
- | |
TOTAL RECOMMENDED | $73,161 | $164,712 |
$1,205
36,049
kWh
|
$1,342
-
kW-mo/yr
|
$31,669
-
MMBtu
|
$(-955.0)
-
MMBtu
|
$9,900
-
lb
|
$30,000 | ||
TOTAL IMPLEMENTED | $72,940 | $164,690 |
$1,100
32,825
kWh
|
$1,226
-
kW-mo/yr
|
$31,669
-
MMBtu
|
$(-955.0)
-
MMBtu
|
$9,900
-
lb
|
$30,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #1 Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs