| Assessment Year | 1996 |
|---|---|
| Principal Product | Sensors |
| NAICS |
n/a
|
| SIC | 3829: Measuring and Controlling Devices, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 170 |
| Plant Area |
81,500
ft2
|
| Annual Production | 65,000
pieces
|
| Production Hrs. Annual | 2,750
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $71,719 | 1,461,606 |
kWh
|
$0.049 |
| Electricity Demand | $31,665 | 6,476 |
kW-mo/yr
|
$4.89 |
| Electricity Fees | $3,626 | - |
|
- |
| Natural Gas | $3,153 | 522 |
MMBtu
|
$6.04 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $8,829 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $5,773 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.3191: Use demand controller or load shedder | $1,105 | $5,000 | - |
$1,105
-
kW-mo/yr
|
- | - | |
| 02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $641 | - | - |
$641
-
kW-mo/yr
|
- | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $549 | $2,100 |
$349
7,327
kWh
|
$50
-
kW-mo/yr
|
- | $150 | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,473 | $6,046 |
$3,081
65,358
kWh
|
$1,392
-
kW-mo/yr
|
- | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $195 | $90 |
$166
3,517
kWh
|
$29
-
kW-mo/yr
|
- | - | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $439 | $400 |
$347
7,327
kWh
|
$92
-
kW-mo/yr
|
- | - | |
| 07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $367 | $367 |
$234
4,982
kWh
|
$133
-
kW-mo/yr
|
- | - | |
| 08 | 2.4226: Use / purchase optimum sized compressor | $1,022 | $320 |
$704
14,947
kWh
|
$318
-
kW-mo/yr
|
- | - | |
| 09 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $38 | $100 | - | - |
$38
-
lb
|
- | |
| TOTAL RECOMMENDED | $8,829 | $14,423 |
$4,881
103,458
kWh
|
$3,760
-
kW-mo/yr
|
$38
-
lb
|
$150 | ||
| TOTAL IMPLEMENTED | $5,773 | $11,136 |
$3,247
68,875
kWh
|
$2,526
-
kW-mo/yr
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs