ITAC Assessment: NC0094
ITAC logo
ITAC Assessment: NC0094
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Vacuum actuators
NAICS
n/a
SIC 3499: Fabricated Metal Products, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 450
Plant Area 130,000
ft2
Annual Production 19,500,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) South Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $435,465 13,160,024
kWh
Electricity Demand $191,527 17,734
kW-mo/yr
Electricity Fees $16,279 -
Natural Gas $29,504 5,030
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $46,604 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $14,049

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (haz) Savings Primary Raw Material Savings Ancillary Material Cost Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,416 $960 $1,536
46,307
kWh
$880
-
kW-mo/yr
- - - - -
02 2.4239: Eliminate or reduce compressed air usage $724 $400 $439
13,189
kWh
$285
-
kW-mo/yr
- - - - -
03 2.4231: Reduce the pressure of compressed air to the minimum required $7,343 $22,000 $4,443
134,232
kWh
$2,900
-
kW-mo/yr
- - - - -
04 2.4239: Eliminate or reduce compressed air usage $1,041 - $629
19,050
kWh
$412
-
kW-mo/yr
- - - - -
05 2.6218: Turn off equipment when not in use $1,770 $20 $1,071
32,239
kWh
$699
-
kW-mo/yr
- - - - -
06 2.7135: Install occupancy sensors $275 $250 $275
8,206
kWh
- - - - - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $100 $420 $49
1,465
kWh
$21
-
kW-mo/yr
- - - - $30
08 2.2443: Re-use or recycle hot or cold process exhaust air $197 $50 $102
2,931
kWh
$95
-
kW-mo/yr
- - - - -
09 3.3131: Use evaporation to concentrate material $11,533 $25,000 - - $(-458.0)
-
MMBtu
- $11,991
-
lb
- -
10 3.4112: Recovery metals from rinse water(evap., ion exchange, ro, electrolysis, electrodialysis) and reuse rinse water $21,205 $54,000 - - $(-535.0)
-
MMBtu
$(-8,000.0)
-
gal
$23,981
-
lb
$5,759 -
TOTAL RECOMMENDED $46,604 $103,100 $8,544
257,619
kWh
$5,292
-
kW-mo/yr
$(-993.0)
-
MMBtu
$(-8,000.0)
-
gal
$35,972
-
lb
$5,759 $30
TOTAL IMPLEMENTED $14,049 $26,380 $1,585
47,772
kWh
$901
-
kW-mo/yr
$(-458.0)
-
MMBtu
- $11,991
-
lb
- $30
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (haz) Savings Primary Raw Material Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs