ITAC Assessment: NC0092
ITAC logo
ITAC Assessment: NC0092
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Tire cord
NAICS
n/a
SIC 2296: Tire Cord and Fabrics
Sales Range $50
M
to 100
M
# of Employees 180
Plant Area 155,000
ft2
Annual Production 22,000,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $854,734 29,945,780
kWh
Electricity Demand $725,928 66,508
kW-mo/yr
Natural Gas $351,263 90,988
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $236,222 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $135,862

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $314 $1,400 $138
4,982
kWh
$76
-
kW-mo/yr
- - $100
02 2.7142: Utilize higher efficiency lamps and/or ballasts $6,972 $708 $3,866
138,042
kWh
$3,106
-
kW-mo/yr
- - -
03 2.4239: Eliminate or reduce compressed air usage $27,124 $60,000 $15,039
537,222
kWh
$12,085
-
kW-mo/yr
- - -
04 2.4133: Use most efficient type of electric motors $30,449 $20,428 $20,580
415,885
kWh
$9,869
-
kW-mo/yr
- - -
05 2.7122: Disconnect ballasts $1,300 $1,430 $720
25,791
kWh
$580
-
kW-mo/yr
- - -
06 2.2694: Use highest temperature for chilling or cold storage $5,891 $50 $1,773
63,306
kWh
$4,118
-
kW-mo/yr
- - -
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $32,148 $1,904 $18,069
645,662
kWh
$14,079
-
kW-mo/yr
- - -
08 2.2515: Use optimum thickness insulation $164 $240 - - $164
-
MMBtu
- -
09 2.5113: Use direct flame impingement or infrared processing for chamber type heating $100,360 $600,000 - - $100,360
-
MMBtu
- -
10 3.3122: Use filtration, centrifuging to remove contaminants $26,400 $10,000 - - - $26,400
-
gal
-
11 3.1162: Use less wasteful packaging $5,100 - - - - - $5,100
TOTAL RECOMMENDED $236,222 $696,160 $60,185
1,830,890
kWh
$43,913
-
kW-mo/yr
$100,524
-
MMBtu
$26,400
-
gal
$5,200
TOTAL IMPLEMENTED $135,862 $96,160 $60,185
1,830,890
kWh
$43,913
-
kW-mo/yr
$164
-
MMBtu
$26,400
-
gal
$5,200
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs