| Assessment Year | 1996 |
|---|---|
| Principal Product | Electric resistance heaters |
| NAICS |
n/a
|
| SIC | 3585: Air-Conditioning and Warm Air Heating Equipment and Commercial and Industrial Refrigeration Equipment |
| Sales Range | $10 M to 50M |
| # of Employees | 350 |
| Plant Area |
386,500
ft2
|
| Annual Production | 700,000
pieces
|
| Production Hrs. Annual | 3,000
hrs
|
| Location (State) | South Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $162,907 | 4,923,212 |
kWh
|
$0.033 |
| Electricity Demand | $154,753 | 14,329 |
kW-mo/yr
|
$10.80 |
| Natural Gas | $143,205 | 28,304 |
MMBtu
|
$5.06 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $29,195 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $18,763 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,208 | $690 |
$509
15,240
kWh
|
$699
-
kW-mo/yr
|
- | - | - | - | - | |
| 02 | 2.4226: Use / purchase optimum sized compressor | $761 | - |
$761
23,154
kWh
|
- | - | - | - | - | - | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $1,464 | $260 |
$511
15,533
kWh
|
$953
-
kW-mo/yr
|
- | - | - | - | - | |
| 04 | 2.2447: Heat water with exhaust heat | $1,007 | $2,000 | - | - |
$1,007
-
MMBtu
|
- | - | - | - | |
| 05 | 3.2121: Convert to electrostatic powder coating | $17,555 | $140,000 |
$2,342
70,633
kWh
|
- | - | - |
$21,390
-
lb
|
$(-12,866.0) | $6,689 | |
| 06 | 3.5316: Contract a wood pallet recycling company | $7,200 | $100 | - | - | - |
$7,200
-
lb
|
- | - | - | |
| TOTAL RECOMMENDED | $29,195 | $143,050 |
$4,123
124,560
kWh
|
$1,652
-
kW-mo/yr
|
$1,007
-
MMBtu
|
$7,200
-
lb
|
$21,390
-
lb
|
$(-12,866.0) | $6,689 | ||
| TOTAL IMPLEMENTED | $18,763 | $140,690 |
$2,851
85,873
kWh
|
$699
-
kW-mo/yr
|
- | - |
$21,390
-
lb
|
$(-12,866.0) | $6,689 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs