Assessment Year | 1996 |
---|---|
Principal Product | Household Clocks |
NAICS |
n/a
|
SIC | 3873: Watches, Clocks, Clockwork Operated Devices, and Parts |
Sales Range | $10 M to 50M |
# of Employees | 425 |
Plant Area |
167,000
ft2
|
Annual Production | 11,000,000
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $222,642 | 6,931,126 |
kWh
|
$0.032 |
Electricity Demand | $137,408 | 10,235 |
kW-mo/yr
|
$13.43 |
Electricity Fees | $16,490 | - |
|
- |
Natural Gas | $13,064 | 2,831 |
MMBtu
|
$4.61 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $51,677 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $30,723 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7122: Disconnect ballasts | $800 | $2,060 |
$387
12,309
kWh
|
$413
-
kW-mo/yr
|
- | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,438 | $17,250 |
$1,012
32,239
kWh
|
$370
-
kW-mo/yr
|
- | - | $2,056 | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,043 | $53,739 |
$6,272
200,469
kWh
|
$4,771
-
kW-mo/yr
|
- | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $558 | $480 |
$398
12,603
kWh
|
$160
-
kW-mo/yr
|
- | - | - | |
05 | 2.4133: Use most efficient type of electric motors | $5,626 | $2,640 |
$4,062
129,836
kWh
|
$1,564
-
kW-mo/yr
|
- | - | - | |
06 | 2.7313: Recycle air for heating, ventilation and air conditioning | $9,258 | $25,000 |
$95
2,931
kWh
|
$418
-
kW-mo/yr
|
$8,745
-
MMBtu
|
- | - | |
07 | 2.7229: Air condition only space necessary | $968 | $1,500 |
$61
2,052
kWh
|
$115
-
kW-mo/yr
|
$792
-
MMBtu
|
- | - | |
08 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $7,816 | - |
$4,028
123,681
kWh
|
$3,788
-
kW-mo/yr
|
- | - | - | |
09 | 3.5314: Use in-process recycling whenever possible | $9,000 | $8,000 | - | - | - |
$25,000
-
lb
|
$(-16,000.0) | |
10 | 3.6192: Use a less expensive method of waste removal | $3,170 | $25,000 |
$(-2,918.0)
(-93,200)
kWh
|
$(-1,552.0)
-
kW-mo/yr
|
- |
$9,820
-
lb
|
$(-2,180.0) | |
TOTAL RECOMMENDED | $51,677 | $135,669 |
$13,397
422,920
kWh
|
$10,047
-
kW-mo/yr
|
$9,537
-
MMBtu
|
$34,820
-
lb
|
$(-16,124.0) | ||
TOTAL IMPLEMENTED | $30,723 | $101,169 |
$12,226
390,387
kWh
|
$7,696
-
kW-mo/yr
|
$8,745
-
MMBtu
|
- | $2,056 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs