Assessment Year | 1994 |
---|---|
Principal Product | Bricks |
NAICS |
n/a
|
SIC | 3251: Brick and Structural Clay Tile |
Sales Range | $10 M to 50M |
# of Employees | 215 |
Plant Area |
273,000
ft2
|
Annual Production | 120,000,000
pieces
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,079,419 | 19,891,266 |
kWh
|
$0.054 |
Natural Gas | $178,171 | 51,555 |
MMBtu
|
$3.46 |
Wood | $409,834 | 569,715 |
MMBtu
|
$0.72 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $235,695 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.2515: Use optimum thickness insulation | $176,704 | $52,500 | n/a | - |
$176,704
-
MMBtu
|
02 | 2.4133: Use most efficient type of electric motors | $16,871 | $27,600 | n/a |
$16,871
312,427
kWh
|
- |
03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $26,900 | $60,000 | n/a |
$26,900
-
kWh
|
- |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $12,452 | $23,090 | n/a |
$12,452
230,657
kWh
|
- |
05 | 2.5194: Redesign process | $2,768 | $782 | n/a | - |
$2,768
-
MMBtu
|
TOTAL RECOMMENDED | $235,695 | $163,972 |
$56,223
543,084
kWh
|
$179,472
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs