ITAC Assessment: NC0012
ITAC logo
ITAC Assessment: NC0012
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Steam Valves
NAICS
n/a
SIC 3492: Fluid Power Valves and Hose Fittings
Sales Range $50
M
to 100
M
# of Employees 232
Plant Area 186,000
ft2
Annual Production 0
units
Production Hrs. Annual 6,000
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $491,134 7,490,035
kWh
Natural Gas $42,834 8,476
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $66,994 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $25,315

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7491: Insulate glazing, walls, ceilings, and roofs $14,358 $14,233 $6,228
94,373
kWh
$8,130
-
MMBtu
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $27,321 - $27,321
-
kWh
-
03 2.1311: Replace electrically-operated equipment with fossil fuel equipment $2,032 $4,500 $4,153
77,081
kWh
$(-2,121.0)
-
MMBtu
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $12,829 $510 $12,829
194,314
kWh
-
05 2.7111: Reduce illumination to minimum necessary levels $10,454 $500 $10,454
158,558
kWh
-
TOTAL RECOMMENDED $66,994 $19,743 $60,985
524,326
kWh
$6,009
-
MMBtu
TOTAL IMPLEMENTED $25,315 $5,510 $27,436
429,953
kWh
$(-2,121.0)
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs