ITAC Assessment: NC0010
ITAC logo
ITAC Assessment: NC0010
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Wood and Laminate Furniture
NAICS
n/a
SIC 2521: Wood Office Furniture
Sales Range $10
M
to 50
M
# of Employees 180
Plant Area 205,000
ft2
Annual Production 0
units
Production Hrs. Annual 4,000
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $207,275 2,938,746
kWh
Natural Gas $52,328 10,820
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $28,948 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,946

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,824 $11,100 $5,824
91,149
kWh
-
02 2.4133: Use most efficient type of electric motors $844 $1,850 $844
13,189
kWh
-
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $3,352 $7,886 $3,352
52,462
kWh
-
04 2.4239: Eliminate or reduce compressed air usage $14,682 $11,000 - $14,682
-
MMBtu
05 2.2449: Recover heat from exhausted steam, hot air or hot water $3,968 - $1,595
24,912
kWh
$2,373
-
MMBtu
06 2.3131: Reschedule plant operations or reduce load to avoid peaks $278 - $278
-
kWh
-
TOTAL RECOMMENDED $28,948 $31,836 $11,893
181,712
kWh
$17,055
-
MMBtu
TOTAL IMPLEMENTED $6,946 $12,950 $6,946
104,338
kWh
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings