ITAC Assessment: MZ1021
ITAC logo
ITAC Assessment: MZ1021
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product City Office
NAICS 531120: Lessors of Nonresidential Buildings (except Miniwarehouses)
SIC 6512: Operators of Nonresidential Buildings
Sales Range less than $500
k
# of Employees 20
Plant Area 8,700
ft2
Annual Production 1
pieces
Production Hrs. Annual 2,340
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $5,410 36,320
kWh
Natural Gas $2,476 221
MMBtu
Waste Disposal Costs
Water Usage $697 19
Tgal
TOTAL YEARLY COSTS $8,583
RECOMMENDED SAVINGS* $4,889 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,526 $3,875 $510
3,425
kWh
- $1,016
02 2.7135: Install occupancy sensors $188 $600 $188
1,264
kWh
- -
03 2.7221: Lower temperature during the winter season and vice-versa $1,199 $240 $382
2,570
kWh
$817
-
MMBtu
-
04 2.2622: Replace existing chiller with high efficiency model $1,976 $17,486 $1,976
13,268
kWh
- -
TOTAL RECOMMENDED $4,889 $22,201 $3,056
20,527
kWh
$817
-
MMBtu
$1,016
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs