| Assessment Year | 2025 |
|---|---|
| Principal Product | Hotel |
| NAICS | 721110: Hotels (except Casino Hotels) and Motels |
| SIC | 7011: Hotels and Motels |
| Sales Range | $50 M to 100M |
| # of Employees | 75 |
| Plant Area |
186,617
ft2
|
| Annual Production | 1
pieces
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $206,144 | 2,549,760 |
kWh
|
$0.081 | |
| Electricity Demand | $24,714 | 5,325 |
kW-mo/yr
|
$4.64 | |
| Natural Gas | $68,051 | 7,134 |
MMBtu
|
$9.54 | |
| Waste Disposal Costs | |||||
| Water Usage | $15,054 | 3,102 |
Tgal
|
$4.85 | |
| Water Disposal | $25,284 | 3,063 |
Tgal
|
$8.26 | |
| TOTAL YEARLY COSTS | $339,247 | ||||
| RECOMMENDED SAVINGS* | $37,249 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $1,704 | $7,400 |
$1,704
21,039
kWh
|
- | - | - | |
| 02 | 2.7135: Install occupancy sensors | $447 | $1,245 |
$447
5,593
kWh
|
- | - | - | |
| 03 | 2.7224: Reduce space conditioning during non-working hours | $1,533 | - |
$851
10,512
kWh
|
- |
$682
-
MMBtu
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,014 | $5,835 |
$5,747
70,956
kWh
|
$451
-
kW-mo/yr
|
- | $816 | |
| 05 | 2.2492: Use "heat wheel" or other heat exchanger to cross-exchange building exhaust air with make-up air | $26,551 | $160,000 |
$6,868
84,795
kWh
|
$538
-
kW-mo/yr
|
$19,145
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $37,249 | $174,480 |
$15,617
192,895
kWh
|
$989
-
kW-mo/yr
|
$19,827
-
MMBtu
|
$816 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs