| Assessment Year | 2025 | 
|---|---|
| Principal Product | Hotel | 
| NAICS | 721110: Hotels (except Casino Hotels) and Motels | 
| SIC | 7011: Hotels and Motels | 
| Sales Range | $1 M  to 5M  | 
    
| # of Employees | 4 | 
| Plant Area | 
                            45,000
                 
ft2
 
                     | 
    
| Annual Production | 1
             
pieces
 
         | 
    
| Production Hrs. Annual | 8,760
             
hrs
 
         | 
    
| Location (State) | Missouri | 
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $33,918 | 429,660 | 
             
kWh
 
         | 
        $0.079 | |
| Electricity Demand | $32,825 | 1,759 | 
             
kW-mo/yr
 
         | 
        $18.66 | |
| Natural Gas | $8,845 | 781 | 
             
MMBtu
 
         | 
        $11.32 | |
| Waste Disposal Costs | |||||
| Water Usage | $22,567 | 6,865 | 
             
Tgal
 
         | 
        $3.29 | |
| Water Disposal | $15,655 | 4,241 | 
             
Tgal
 
         | 
        $3.69 | |
| TOTAL YEARLY COSTS | $113,810 | ||||
| RECOMMENDED SAVINGS* | $1,119 | 
             See individual recommendations below 
            *Non-energy impacts included in savings.
         | 
    |||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings | 
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2515: Use optimum thickness insulation | $244 | $634 | - | - | 
                        $244
                                                     -
                                 
                                            
MMBtu
 
                             | 
                                                                                - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $533 | $700 | 
                        $239
                                                     3,066
                                 
                                            
kWh
 
                             | 
                                                                                
                        $112
                                                     -
                                 
                                            
kW-mo/yr
 
                             | 
                                                                                - | $182 | |
| 03 | 2.6218: Turn off equipment when not in use | $342 | $60 | 
                        $249
                                                     3,154
                                 
                                            
kWh
 
                             | 
                                                                                
                        $93
                                                     -
                                 
                                            
kW-mo/yr
 
                             | 
                                                                                - | - | |
| TOTAL RECOMMENDED | $1,119 | $1,394 | 
                        $488
                                                     6,220
                                 
                                            
kWh
 
                             | 
                                                                                
                        $205
                                                     -
                                 
                                            
kW-mo/yr
 
                             | 
                                                                                
                        $244
                                                     -
                                 
                                            
MMBtu
 
                             | 
                                                                                $182 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs