Assessment Year | 2025 |
---|---|
Principal Product | Hotel |
NAICS | 721110: Hotels (except Casino Hotels) and Motels |
SIC | 7011: Hotels and Motels |
Sales Range | less than $500 k |
# of Employees | 30 |
Plant Area |
153,000
ft2
|
Annual Production | 1
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $125,360 | 1,583,200 |
kWh
|
$0.079 | |
Electricity Demand | $59,005 | 3,270 |
kW-mo/yr
|
$18.04 | |
Natural Gas | $55,449 | 5,127 |
MMBtu
|
$10.82 | |
Waste Disposal Costs | |||||
Water Usage | $22,817 | 4,105 |
Tgal
|
$5.56 | |
Water Disposal | $26,737 | 4,105 |
Tgal
|
$6.51 | |
TOTAL YEARLY COSTS | $289,368 | ||||
RECOMMENDED SAVINGS* | $33,813 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,677 | $4,600 |
$2,677
33,805
kWh
|
- | - | - | |
02 | 2.9112: Use solar heat to heat water | $3,319 | $23,760 | - | - |
$3,319
-
MMBtu
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $517 | $496 |
$294
3,726
kWh
|
$90
-
kW-mo/yr
|
- | $133 | |
04 | 2.1321: Replace fossil fuel equipment with electrical equipment | $14,776 | $6,332 |
$(-1,195.0)
(-15,120)
kWh
|
$(-379.0)
-
kW-mo/yr
|
$16,350
-
MMBtu
|
- | |
05 | 2.6121: Reduce hot water temperature to the minimum required | $789 | - | - | - |
$789
-
MMBtu
|
- | |
06 | 2.2625: Chill water to the highest temperature possible | $5,010 | $8,640 |
$5,010
63,418
kWh
|
- | - | - | |
07 | 2.2628: Utilize a less expensive cooling method | $3,409 | $3,750 |
$1,245
15,768
kWh
|
$2,164
-
kW-mo/yr
|
- | - | |
08 | 2.7314: Reduce ventilation air | $3,316 | $5,000 |
$3,316
41,975
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $33,813 | $52,578 |
$11,347
143,572
kWh
|
$1,875
-
kW-mo/yr
|
$20,458
-
MMBtu
|
$133 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs