ITAC Assessment: MZ1015
ITAC logo
ITAC Assessment: MZ1015
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Hotel
NAICS 721110: Hotels (except Casino Hotels) and Motels
SIC 7011: Hotels and Motels
Sales Range less than $500
k
# of Employees 30
Plant Area 153,000
ft2
Annual Production 1
pieces
Production Hrs. Annual 8,760
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $125,360 1,583,200
kWh
Electricity Demand $59,005 3,270
kW-mo/yr
Natural Gas $55,449 5,127
MMBtu
Waste Disposal Costs
Water Usage $22,817 4,105
Tgal
Water Disposal $26,737 4,105
Tgal
TOTAL YEARLY COSTS $289,368
RECOMMENDED SAVINGS* $33,813 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,677 $4,600 $2,677
33,805
kWh
- - -
02 2.9112: Use solar heat to heat water $3,319 $23,760 - - $3,319
-
MMBtu
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $517 $496 $294
3,726
kWh
$90
-
kW-mo/yr
- $133
04 2.1321: Replace fossil fuel equipment with electrical equipment $14,776 $6,332 $(-1,195.0)
(-15,120)
kWh
$(-379.0)
-
kW-mo/yr
$16,350
-
MMBtu
-
05 2.6121: Reduce hot water temperature to the minimum required $789 - - - $789
-
MMBtu
-
06 2.2625: Chill water to the highest temperature possible $5,010 $8,640 $5,010
63,418
kWh
- - -
07 2.2628: Utilize a less expensive cooling method $3,409 $3,750 $1,245
15,768
kWh
$2,164
-
kW-mo/yr
- -
08 2.7314: Reduce ventilation air $3,316 $5,000 $3,316
41,975
kWh
- - -
TOTAL RECOMMENDED $33,813 $52,578 $11,347
143,572
kWh
$1,875
-
kW-mo/yr
$20,458
-
MMBtu
$133
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs