ITAC Assessment: MZ1007
ITAC logo
ITAC Assessment: MZ1007
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product City Hall
NAICS 921120: Legislative Bodies
SIC 6221: Commodity Contracts Brokers and Dealers
Sales Range less than $500
k
# of Employees 12
Plant Area 29,200
ft2
Annual Production 1
pieces
Production Hrs. Annual 2,250
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $43,536 366,364
kWh
Natural Gas $1,742 133
MMBtu
TOTAL YEARLY COSTS $45,278
RECOMMENDED SAVINGS* $2,991 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.2511: Insulate bare equipment $318 $1,546 $318
2,674
kWh
-
02 2.2622: Replace existing chiller with high efficiency model $2,494 $11,880 $2,494
20,960
kWh
-
03 2.9112: Use solar heat to heat water $179 $2,100 - $179
-
MMBtu
TOTAL RECOMMENDED $2,991 $15,526 $2,812
23,634
kWh
$179
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs