Assessment Year | 2025 |
---|---|
Principal Product | cutting tools |
NAICS | 333517: Machine Tool Manufacturing |
SIC | 3545: Cutting Tools, Machine Tool Accessories, and Machinists' Precision Measuring Devices |
Sales Range | $10 M to 50M |
# of Employees | 450 |
Plant Area |
255,000
ft2
|
Annual Production | 10,950,000
pieces
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $685,513 | 7,908,953 |
kWh
|
$0.087 |
Electricity Demand | $163,955 | 20,308 |
kW-mo/yr
|
$8.07 |
Natural Gas | $46,294 | 4,520 |
MMBtu
|
$10.24 |
TOTAL YEARLY COSTS | $895,762 | |||
RECOMMENDED SAVINGS* | $242,618 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,972 | $3,500 |
$1,972
22,742
kWh
|
- | - | |
02 | 2.7111: Reduce illumination to minimum necessary levels | $26,585 | $49,000 |
$26,585
306,638
kWh
|
- | - | |
03 | 2.7135: Install occupancy sensors | $4,373 | $750 |
$4,373
50,442
kWh
|
- | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,470 | $750 |
$2,197
25,150
kWh
|
$273
-
kW-mo/yr
|
- | |
05 | 2.2437: Recover waste heat from equipment | $10,844 | $12,060 | - | - |
$10,844
-
MMBtu
|
|
06 | 2.9114: Use solar heat to make electricty | $196,374 | $1,560,000 |
$188,180
2,170,469
kWh
|
$8,194
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $242,618 | $1,626,060 |
$223,307
2,575,441
kWh
|
$8,467
-
kW-mo/yr
|
$10,844
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs