ITAC Assessment: MZ0378
ITAC logo
ITAC Assessment: MZ0378
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product cutting tools
NAICS 333517: Machine Tool Manufacturing
SIC 3545: Cutting Tools, Machine Tool Accessories, and Machinists' Precision Measuring Devices
Sales Range $10
M
to 50
M
# of Employees 450
Plant Area 255,000
ft2
Annual Production 10,950,000
pieces
Production Hrs. Annual 4,420
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $685,513 7,908,953
kWh
Electricity Demand $163,955 20,308
kW-mo/yr
Natural Gas $46,294 4,520
MMBtu
TOTAL YEARLY COSTS $895,762
RECOMMENDED SAVINGS* $242,618 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,972 $3,500 $1,972
22,742
kWh
- -
02 2.7111: Reduce illumination to minimum necessary levels $26,585 $49,000 $26,585
306,638
kWh
- -
03 2.7135: Install occupancy sensors $4,373 $750 $4,373
50,442
kWh
- -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,470 $750 $2,197
25,150
kWh
$273
-
kW-mo/yr
-
05 2.2437: Recover waste heat from equipment $10,844 $12,060 - - $10,844
-
MMBtu
06 2.9114: Use solar heat to make electricty $196,374 $1,560,000 $188,180
2,170,469
kWh
$8,194
-
kW-mo/yr
-
TOTAL RECOMMENDED $242,618 $1,626,060 $223,307
2,575,441
kWh
$8,467
-
kW-mo/yr
$10,844
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs