ITAC Assessment: MZ0339
ITAC logo
ITAC Assessment: MZ0339
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product disposable surgical instruments
NAICS 339112: Surgical and Medical Instrument Manufacturing
SIC 3841: Surgical and Medical Instruments and Apparatus
Sales Range $10
M
to 50
M
# of Employees 180
Plant Area 62,000
ft2
Annual Production 500,000
pieces
Production Hrs. Annual 5,200
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $128,882 1,666,800
kWh
Electricity Demand $14,682 4,022
kW-mo/yr
Natural Gas $12,747 1,411
MMBtu
Waste Disposal Costs
Water Usage $4,965 908
Tgal
TOTAL YEARLY COSTS $161,276
RECOMMENDED SAVINGS* $12,094 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,636

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $9,822 $6,511 $9,822
129,262
kWh
-
02 2.4239: Eliminate or reduce compressed air usage $1,100 $8,100 $990
13,034
kWh
$110
-
kW-mo/yr
03 2.4239: Eliminate or reduce compressed air usage $440 $450 $396
5,214
kWh
$44
-
kW-mo/yr
04 2.4239: Eliminate or reduce compressed air usage $196 $289 $196
2,578
kWh
-
05 2.7135: Install occupancy sensors $536 $1,120 $536
7,043
kWh
-
TOTAL RECOMMENDED $12,094 $16,470 $11,940
157,131
kWh
$154
-
kW-mo/yr
TOTAL IMPLEMENTED $1,636 $9,220 $1,526
20,077
kWh
$110
-
kW-mo/yr
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs