ITAC Assessment: MZ0331
ITAC logo
ITAC Assessment: MZ0331
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product lead acid batteries
NAICS 335911: Storage Battery Manufacturing
SIC 3691: Storage Batteries
Sales Range $100
M
to 500
M
# of Employees 495
Plant Area 504,400
ft2
Annual Production 63,876,869
lb
Production Hrs. Annual 6,864
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $2,387,309 54,865,902
kWh
Electricity Demand $1,062,735 101,312
kW-mo/yr
Natural Gas $331,584 177,721
MMBtu
Waste Disposal Costs
Water Usage $173,288 43,433
Tgal
Water Disposal $310,645 43,427
Tgal
TOTAL YEARLY COSTS $4,265,561
RECOMMENDED SAVINGS* $759,848 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $170,570

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings One-time Revenue or Avoided Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $23,162 $25,757 $16,274
378,841
kWh
$6,888
-
kW-mo/yr
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $18,037 $46,350 $7,878
183,217
kWh
$5,209
-
kW-mo/yr
- $4,950
03 3.4116: Meter recycled water (to reduce sewer charges) $91,773 $9,040 - - $91,773
-
Tgal
-
04 2.4239: Eliminate or reduce compressed air usage $5,985 $29,286 $2,373
55,195
kWh
$3,612
-
kW-mo/yr
- -
05 2.2622: Replace existing chiller with high efficiency model $402,938 $1,820,000 $263,527
6,128,535
kWh
$139,411
-
kW-mo/yr
- -
06 2.7243: Improve air circulation with destratification fans / other methods $31,613 $98,280 $22,213
516,584
kWh
$9,400
-
kW-mo/yr
- -
07 2.7273: Install desiccant humidity control system $76,144 $423,000 $47,756
1,110,595
kWh
$28,388
-
kW-mo/yr
- -
08 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $110,196 $55,220 $110,196
2,562,689
kWh
- - -
TOTAL RECOMMENDED $759,848 $2,506,933 $470,217
10,935,656
kWh
$192,908
-
kW-mo/yr
$91,773
-
Tgal
$4,950
TOTAL IMPLEMENTED $170,570 $208,713 $48,738
1,133,837
kWh
$25,109
-
kW-mo/yr
$91,773
-
Tgal
$4,950
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Disposal Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs