| Assessment Year | 2021 |
|---|---|
| Principal Product | Prefabricated Metal Buildings |
| NAICS | 332311: Prefabricated Metal Building and Component Manufacturing |
| SIC | 3448: Prefabricated Metal Buildings and Components |
| Sales Range | $10 M to 50M |
| # of Employees | 45 |
| Plant Area |
215,000
ft2
|
| Annual Production | 500
units
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | Kansas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $84,224 | 881,028 |
kWh
|
$0.096 | |
| Electricity Demand | $17,414 | 2,785 |
kW-mo/yr
|
$6.25 | |
| Electricity Fees | $622 | - |
|
- | |
| Natural Gas | $23,699 | 4,867 |
MMBtu
|
$4.87 | |
| Waste Disposal Costs | |||||
| Water Usage | $8,074 | 219 |
Tgal
|
$36.87 | |
| TOTAL YEARLY COSTS | $134,033 | ||||
| RECOMMENDED SAVINGS* | $13,319 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.6218: Turn off equipment when not in use | $6,274 | $490 |
$6,274
65,624
kWh
|
- | - | |
| 02 | 2.8115: Base utility charges on usage rather than area occupied | $3,630 | $1,160 | - | - | $3,630 | |
| 03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,250 | $2,580 | - |
$2,250
-
kW-mo/yr
|
- | |
| 04 | 2.4239: Eliminate or reduce compressed air usage | $1,165 | $1,896 |
$1,069
11,178
kWh
|
$96
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $13,319 | $6,126 |
$7,343
76,802
kWh
|
$2,346
-
kW-mo/yr
|
$3,630 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs