Assessment Year | 2020 |
---|---|
Principal Product | Nonferrous aluminum and copper investment castings |
NAICS | 331524: Aluminum Foundries (except Die-Casting) |
SIC | 3365: Aluminum Foundries |
Sales Range | $10 M to 50M |
# of Employees | 180 |
Plant Area |
72,000
ft2
|
Annual Production | 207,326
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $401,346 | 6,024,960 |
kWh
|
$0.067 | |
Electricity Demand | $51,669 | 15,692 |
kW-mo/yr
|
$3.29 | |
Natural Gas | $81,468 | 17,821 |
MMBtu
|
$4.57 | |
Waste Disposal Costs | |||||
Water Usage | $8,362 | 20 |
Tgal
|
$426.45 | |
TOTAL YEARLY COSTS | $542,845 | ||||
RECOMMENDED SAVINGS* | $26,763 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2424: Use heat in flue gases to preheat products or materials | $22,302 | $48,220 | - | - |
$22,302
-
MMBtu
|
- | |
02 | 2.7144: Install spectral reflectors / delamp | $1,877 | $396 |
$1,017
15,418
kWh
|
$68
-
kW-mo/yr
|
- | $792 | |
03 | 2.7135: Install occupancy sensors | $98 | $250 |
$98
1,458
kWh
|
- | - | - | |
04 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,486 | $720 | - | - |
$2,486
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $26,763 | $49,586 |
$1,115
16,876
kWh
|
$68
-
kW-mo/yr
|
$24,788
-
MMBtu
|
$792 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs