ITAC Assessment: MZ0263
ITAC logo
ITAC Assessment: MZ0263
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product wastewater and sewage treatment
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range less than $500
k
# of Employees 2
Plant Area 4,800
ft2
Annual Production 350,000
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $110,882 1,410,850
kWh
Electricity Demand $19,845 2,739
kW-mo/yr
TOTAL YEARLY COSTS $130,726
RECOMMENDED SAVINGS* $5,815 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,815

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings One-time Revenue or Avoided Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,735 $2,278 $1,193
15,300
kWh
$278
-
kW-mo/yr
$264
02 2.3191: Use demand controller or load shedder $2,027 $7,760 - $2,027
-
kW-mo/yr
-
03 2.3212: Optimize plant power factor $2,053 $2,760 - $2,053
-
kW-mo/yr
-
TOTAL RECOMMENDED $5,815 $12,798 $1,193
15,300
kWh
$4,358
-
kW-mo/yr
$264
TOTAL IMPLEMENTED $5,815 $12,798 $1,193
15,300
kWh
$4,358
-
kW-mo/yr
$264
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs