ITAC Assessment: MZ0252
ITAC logo
ITAC Assessment: MZ0252
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product milled carbon fiber and chopped carbon fiber
NAICS 335991: Carbon and Graphite Product Manufacturing
SIC 3624: Carbon and Graphite Products
Sales Range $10
M
to 50
M
# of Employees 12
Plant Area 107,000
ft2
Annual Production 14,146,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $309,391 4,611,603
kWh
Electricity Demand $33,994 12,732
kW-mo/yr
Natural Gas $112,296 28,662
MMBtu
TOTAL YEARLY COSTS $455,680
RECOMMENDED SAVINGS* $76,101 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $75,445

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings One-time Revenue or Avoided Cost Savings
01 2.7144: Install spectral reflectors / delamp $4,011 $540 $3,803
56,765
kWh
$208
-
kW-mo/yr
-
02 2.4133: Use most efficient type of electric motors $4,478 $32,500 $4,247
63,386
kWh
$231
-
kW-mo/yr
-
03 2.4239: Eliminate or reduce compressed air usage $656 $4,200 $515
7,692
kWh
$141
-
kW-mo/yr
-
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,159 - $1,099
16,406
kWh
$60
-
kW-mo/yr
-
05 4.132: Purchase new equipment to reduce material use / cost $65,281 $50,000 $(-5,282.0)
(-78,840)
kWh
$(-481.0)
-
kW-mo/yr
$71,044
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $516 $50 $441
6,586
kWh
$75
-
kW-mo/yr
-
TOTAL RECOMMENDED $76,101 $87,290 $4,823
71,995
kWh
$234
-
kW-mo/yr
$71,044
TOTAL IMPLEMENTED $75,445 $83,090 $4,308
64,303
kWh
$93
-
kW-mo/yr
$71,044
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs