Assessment Year | 2017 |
---|---|
Principal Product | powder metallurgy parts |
NAICS | 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing |
SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 60 |
Plant Area |
100,000
ft2
|
Annual Production | 1,200,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $238,828 | 5,208,800 |
kWh
|
$0.046 | |
Electricity Demand | $82,122 | 9,894 |
kW-mo/yr
|
$8.30 | |
Natural Gas | $80,826 | 26,786 |
MMBtu
|
$3.02 | |
Waste Disposal Costs | |||||
Water Usage | $3,208 | 1,791,000 |
Tgal
|
$0.002 | |
TOTAL YEARLY COSTS | $404,984 | ||||
RECOMMENDED SAVINGS* | $12,766 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $4,922 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $407 | $2,000 |
$407
8,856
kWh
|
- | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,800 | - |
$1,800
39,125
kWh
|
- | |
03 | 2.7135: Install occupancy sensors | $1,354 | $1,550 |
$1,005
21,852
kWh
|
$349
-
kW-mo/yr
|
|
04 | 2.4239: Eliminate or reduce compressed air usage | $5,248 | $5,940 |
$5,248
114,078
kWh
|
- | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,596 | - |
$1,927
41,895
kWh
|
$669
-
kW-mo/yr
|
|
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,361 | $50 |
$1,002
21,790
kWh
|
$359
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $12,766 | $9,540 |
$11,389
247,596
kWh
|
$1,377
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $4,922 | $3,600 |
$4,214
91,623
kWh
|
$708
-
kW-mo/yr
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs