| Assessment Year | 2016 |
|---|---|
| Principal Product | Automobile instrumentation |
| NAICS | 334515: Instrument Manufacturing for Measuring and Testing Electricity and Electrical Signals |
| SIC | 3825: Instruments for Measuring and Testing of Electricity and Electrical Signals |
| Sales Range | $10 M to 50M |
| # of Employees | 60 |
| Plant Area |
63,000
ft2
|
| Annual Production | 3,000
units
|
| Production Hrs. Annual | 4,300
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $91,671 | 1,222,280 |
kWh
|
$0.075 |
| Electricity Demand | $14,706 | 4,525 |
kW-mo/yr
|
$3.25 |
| Natural Gas | $17,356 | 1,550 |
MMBtu
|
$11.20 |
| TOTAL YEARLY COSTS | $123,733 | |||
| RECOMMENDED SAVINGS* | $18,225 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $11,337 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7232: Replace existing hvac unit with high efficiency model | $3,078 | $12,500 |
$2,798
37,308
kWh
|
$280
-
kW-mo/yr
|
- | |
| 02 | 2.7134: Use photocell controls | $2,869 | $490 |
$2,869
38,250
kWh
|
- | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,572 | $10,350 |
$4,078
54,374
kWh
|
$494
-
kW-mo/yr
|
- | |
| 04 | 2.7135: Install occupancy sensors | $2,293 | $900 |
$2,293
30,579
kWh
|
- | - | |
| 05 | 2.7221: Lower temperature during the winter season and vice-versa | $3,810 | - |
$1,357
18,092
kWh
|
$146
-
kW-mo/yr
|
$2,307
-
MMBtu
|
|
| 06 | 2.7135: Install occupancy sensors | $1,603 | $900 |
$1,603
21,375
kWh
|
- | - | |
| TOTAL RECOMMENDED | $18,225 | $25,140 |
$14,998
199,978
kWh
|
$920
-
kW-mo/yr
|
$2,307
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $11,337 | $12,640 |
$10,843
144,578
kWh
|
$494
-
kW-mo/yr
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs