| Assessment Year | 2016 |
|---|---|
| Principal Product | packaged food |
| NAICS | 311412: Frozen Specialty Food Manufacturing |
| SIC | 2038: Frozen Specialties, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 35 |
| Plant Area |
46,000
ft2
|
| Annual Production | 2,800,000
pieces
|
| Production Hrs. Annual | 4,900
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $63,542 | 1,064,848 |
kWh
|
$0.060 |
| Electricity Demand | $14,695 | 2,765 |
kW-mo/yr
|
$5.31 |
| Natural Gas | $29,973 | 3,885 |
MMBtu
|
$7.72 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $11,571 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $11,004 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,397 | $8,400 |
$6,074
101,789
kWh
|
$1,323
-
kW-mo/yr
|
- | |
| 02 | 2.2511: Insulate bare equipment | $2,514 | $1,500 |
$2,238
37,513
kWh
|
$276
-
kW-mo/yr
|
- | |
| 03 | 2.7135: Install occupancy sensors | $1,093 | $220 |
$1,093
18,320
kWh
|
- | - | |
| 04 | 2.7221: Lower temperature during the winter season and vice-versa | $567 | - |
$244
4,095
kWh
|
$53
-
kW-mo/yr
|
$270
-
MMBtu
|
|
| TOTAL RECOMMENDED | $11,571 | $10,120 |
$9,649
161,717
kWh
|
$1,652
-
kW-mo/yr
|
$270
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $11,004 | $10,120 |
$9,405
157,622
kWh
|
$1,599
-
kW-mo/yr
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs