ITAC Assessment: MZ0208
ITAC logo
ITAC Assessment: MZ0208
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product vending machines
NAICS 333318: Other Commercial and Service Industry Machinery Manufacturing
SIC 3581: Automatic Vending Machines
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area 65,000
ft2
Annual Production 10,000
units
Production Hrs. Annual 8,500
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $105,596 1,443,088
kWh
Electricity Demand $48,486 5,154
kW-mo/yr
Other Energy $600,000 26,929
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $127,597 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $127,518

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Energy Savings
01 2.2511: Insulate bare equipment $79 $200 $79
1,073
kWh
- - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $6,161 $6,600 $5,220
71,337
kWh
$941
-
kW-mo/yr
- -
03 2.7135: Install occupancy sensors $3,247 $1,250 $3,247
44,376
kWh
- - -
04 2.1335: Replace gasoline with diesel, lpg, or natural gas $118,110 $525,000 - - $(-481,890.0)
-
MMBtu
$600,000
-
MMBtu
TOTAL RECOMMENDED $127,597 $533,050 $8,546
116,786
kWh
$941
-
kW-mo/yr
$(-481,890.0)
-
MMBtu
$600,000
-
MMBtu
TOTAL IMPLEMENTED $127,518 $532,850 $8,467
115,713
kWh
$941
-
kW-mo/yr
$(-481,890.0)
-
MMBtu
$600,000
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs