ITAC Assessment: MZ0184
ITAC logo
ITAC Assessment: MZ0184
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Display cabinets
NAICS 337215: Showcase, Partition, Shelving, and Locker Manufacturing
SIC 2541: Wood Office and Store Fixtures, Partitions, Shelving, and Lockers
Sales Range $10
M
to 50
M
# of Employees 68
Plant Area 101,200
ft2
Annual Production 60,000
pieces
Production Hrs. Annual 5,500
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $132,612 2,380,783
kWh
Electricity Demand $27,959 4,648
kW-mo/yr
Natural Gas $30,651 3,621
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $35,905 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $30,294

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $28,705 $78,480 $23,231
417,065
kWh
$5,474
-
kW-mo/yr
-
02 2.4239: Eliminate or reduce compressed air usage $357 $1,750 $289
5,190
kWh
$68
-
kW-mo/yr
-
03 2.4239: Eliminate or reduce compressed air usage $5,611 $12,500 $4,805
86,267
kWh
$806
-
kW-mo/yr
-
04 2.7221: Lower temperature during the winter season and vice-versa $1,232 - - - $1,232
-
MMBtu
TOTAL RECOMMENDED $35,905 $92,730 $28,325
508,522
kWh
$6,348
-
kW-mo/yr
$1,232
-
MMBtu
TOTAL IMPLEMENTED $30,294 $80,230 $23,520
422,255
kWh
$5,542
-
kW-mo/yr
$1,232
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs