| Assessment Year | 2014 |
|---|---|
| Principal Product | zinc plating |
| NAICS | 332813: Electroplating, Plating, Polishing, Anodizing, and Coloring |
| SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
| Sales Range | $1 M to 5M |
| # of Employees | 27 |
| Plant Area |
39,000
ft2
|
| Annual Production | 15,000,000
thousand feet
|
| Production Hrs. Annual | 7,350
hrs
|
| Location (State) | Illinois |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $86,103 | 1,929,488 |
kWh
|
$0.045 |
| Electricity Demand | $27,353 | 5,165 |
kW-mo/yr
|
$5.30 |
| Natural Gas | $119,884 | 27,144 |
MMBtu
|
$4.42 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $42,967 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $17,190 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2514: Cover open tanks | $6,406 | $5,250 | - | - |
$6,406
-
MMBtu
|
|
| 02 | 2.2511: Insulate bare equipment | $9,563 | $12,000 | - | - |
$9,563
-
MMBtu
|
|
| 03 | 2.2511: Insulate bare equipment | $824 | $900 |
$692
15,521
kWh
|
$132
-
kW-mo/yr
|
- | |
| 04 | 2.4131: Size electric motors for peak operating efficiency | $13,431 | $4,400 |
$11,250
252,252
kWh
|
$2,181
-
kW-mo/yr
|
- | |
| 05 | 2.4133: Use most efficient type of electric motors | $2,120 | $7,400 |
$2,120
47,550
kWh
|
- | - | |
| 06 | 2.2414: Use waste heat from hot flue gases to preheat | $5,940 | $5,500 | - | - |
$5,940
-
MMBtu
|
|
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,683 | $15,640 |
$3,923
87,965
kWh
|
$760
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $42,967 | $51,090 |
$17,985
403,288
kWh
|
$3,073
-
kW-mo/yr
|
$21,909
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $17,190 | $35,940 |
$6,735
151,036
kWh
|
$892
-
kW-mo/yr
|
$9,563
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs