ITAC Assessment: MZ0138
ITAC logo
ITAC Assessment: MZ0138
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product fasteners, machined parts
NAICS 332721: Precision Turned Product Manufacturing
SIC 3452: Bolts, Nuts, Screws, Rivets, and Washers
Sales Range $10
M
to 50
M
# of Employees 36
Plant Area 59,000
ft2
Annual Production 6,000,000
pieces
Production Hrs. Annual 4,600
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $101,476 1,373,400
kWh
Electricity Demand $13,550 5,023
kW-mo/yr
Natural Gas $83,367 8,757
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $13,362 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $915

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.2511: Insulate bare equipment $871 $620 - $871
-
MMBtu
02 2.2437: Recover waste heat from equipment $557 $1,075 - $557
-
MMBtu
03 2.2414: Use waste heat from hot flue gases to preheat $8,006 $15,000 - $8,006
-
MMBtu
04 2.7229: Air condition only space necessary $3,570 - - $3,570
-
MMBtu
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $358 - $358
4,844
kWh
-
TOTAL RECOMMENDED $13,362 $16,695 $358
4,844
kWh
$13,004
-
MMBtu
TOTAL IMPLEMENTED $915 $1,075 $358
4,844
kWh
$557
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs