Assessment Year | 2014 |
---|---|
Principal Product | fasteners, machined parts |
NAICS | 332721: Precision Turned Product Manufacturing |
SIC | 3452: Bolts, Nuts, Screws, Rivets, and Washers |
Sales Range | $10 M to 50M |
# of Employees | 36 |
Plant Area |
59,000
ft2
|
Annual Production | 6,000,000
pieces
|
Production Hrs. Annual | 4,600
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $101,476 | 1,373,400 |
kWh
|
$0.074 |
Electricity Demand | $13,550 | 5,023 |
kW-mo/yr
|
$2.70 |
Natural Gas | $83,367 | 8,757 |
MMBtu
|
$9.52 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $13,362 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $915 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.2511: Insulate bare equipment | $871 | $620 | - |
$871
-
MMBtu
|
|
02 | 2.2437: Recover waste heat from equipment | $557 | $1,075 | - |
$557
-
MMBtu
|
|
03 | 2.2414: Use waste heat from hot flue gases to preheat | $8,006 | $15,000 | - |
$8,006
-
MMBtu
|
|
04 | 2.7229: Air condition only space necessary | $3,570 | - | - |
$3,570
-
MMBtu
|
|
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $358 | - |
$358
4,844
kWh
|
- | |
TOTAL RECOMMENDED | $13,362 | $16,695 |
$358
4,844
kWh
|
$13,004
-
MMBtu
|
||
TOTAL IMPLEMENTED | $915 | $1,075 |
$358
4,844
kWh
|
$557
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs