Assessment Year | 2013 |
---|---|
Principal Product | Recycled metals |
NAICS | 331314: Secondary Smelting and Alloying of Aluminum |
SIC | 3341: Secondary Smelting and Refining of Nonferrous Metals |
Sales Range | $10 M to 50M |
# of Employees | 41 |
Plant Area |
653,400
ft2
|
Annual Production | 10,000
ton
|
Production Hrs. Annual | 2,210
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $120,963 | 3,076,484 |
kWh
|
$0.039 |
Electricity Demand | $254,056 | 33,069 |
kW-mo/yr
|
$7.68 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $13,299 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,501 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $7,531 | $32,100 |
$3,653
92,960
kWh
|
$3,878
-
kW-mo/yr
|
|
02 | 2.7135: Install occupancy sensors | $3,501 | $780 |
$3,501
89,073
kWh
|
- | |
03 | 2.2437: Recover waste heat from equipment | $1,939 | $770 |
$941
23,947
kWh
|
$998
-
kW-mo/yr
|
|
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $328 | $575 |
$159
4,054
kWh
|
$169
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $13,299 | $34,225 |
$8,254
210,034
kWh
|
$5,045
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $3,501 | $780 |
$3,501
89,073
kWh
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs