Assessment Year | 2013 |
---|---|
Principal Product | automotive braking systems |
NAICS | 336340: Motor Vehicle Brake System Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $50 M to 100M |
# of Employees | 270 |
Plant Area |
110,000
ft2
|
Annual Production | 2,374,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $153,204 | 2,554,942 |
kWh
|
$0.060 |
Electricity Demand | $56,907 | 7,732 |
kW-mo/yr
|
$7.36 |
Natural Gas | $20,391 | 2,043 |
MMBtu
|
$9.98 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $70,522 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $24,016 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,890 | $900 |
$3,127
53,914
kWh
|
$763
-
kW-mo/yr
|
- | |
02 | 2.2437: Recover waste heat from equipment | $10,497 | $15,000 | - | - |
$10,497
-
MMBtu
|
|
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,319 | - |
$3,319
55,498
kWh
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $18,532 | $45,540 |
$14,985
250,585
kWh
|
$3,547
-
kW-mo/yr
|
- | |
05 | 2.7229: Air condition only space necessary | $32,690 | $12,531 |
$24,361
407,376
kWh
|
$8,329
-
kW-mo/yr
|
- | |
06 | 2.4227: Use compressor air filters | $1,594 | $850 |
$1,289
21,556
kWh
|
$305
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $70,522 | $74,821 |
$47,081
788,929
kWh
|
$12,944
-
kW-mo/yr
|
$10,497
-
MMBtu
|
||
TOTAL IMPLEMENTED | $24,016 | $47,290 |
$19,401
326,055
kWh
|
$4,615
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs