| Assessment Year | 2013 |
|---|---|
| Principal Product | aluminum castings |
| NAICS | 331315: Aluminum Sheet, Plate, and Foil Manufacturing |
| SIC | 3365: Aluminum Foundries |
| Sales Range | $10 M to 50M |
| # of Employees | 120 |
| Plant Area |
145,000
ft2
|
| Annual Production | 1
units
|
| Production Hrs. Annual | 6,720
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $518,870 | 7,041,600 |
kWh
|
$0.074 |
| Electricity Demand | $86,995 | 18,912 |
kW-mo/yr
|
$4.60 |
| Natural Gas | $180,956 | 39,149 |
MMBtu
|
$4.62 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $76,763 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $41,522 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $28,136 | $119,770 |
$24,898
336,462
kWh
|
$3,238
-
kW-mo/yr
|
- | |
| 02 | 2.2424: Use heat in flue gases to preheat products or materials | $35,241 | $75,000 | - | - |
$35,241
-
MMBtu
|
|
| 03 | 2.2622: Replace existing chiller with high efficiency model | $8,557 | $31,200 |
$3,424
46,269
kWh
|
$5,133
-
kW-mo/yr
|
- | |
| 04 | 2.7135: Install occupancy sensors | $153 | $190 |
$153
2,070
kWh
|
- | - | |
| 05 | 2.4227: Use compressor air filters | $4,675 | $1,100 |
$4,246
57,381
kWh
|
$429
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $76,763 | $227,260 |
$32,722
442,183
kWh
|
$8,800
-
kW-mo/yr
|
$35,241
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $41,522 | $152,260 |
$32,722
442,183
kWh
|
$8,800
-
kW-mo/yr
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs