| Assessment Year | 2013 |
|---|---|
| Principal Product | aluminum castings |
| NAICS | 331524: Aluminum Foundries (except Die-Casting) |
| SIC | 3365: Aluminum Foundries |
| Sales Range | $10 M to 50M |
| # of Employees | 86 |
| Plant Area |
400,000
ft2
|
| Annual Production | 2,000,000
pieces
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $410,209 | 7,088,400 |
kWh
|
$0.058 |
| Electricity Demand | $95,044 | 5,796 |
kW-mo/yr
|
$16.40 |
| Natural Gas | $379,653 | 15,186 |
MMBtu
|
$25.00 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $148,477 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $114,678 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4221: Install compressor air intakes in coolest locations | $7,869 | $3,480 |
$4,257
73,406
kWh
|
$3,612
-
kW-mo/yr
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,761 | $39,840 |
$6,904
119,040
kWh
|
$5,857
-
kW-mo/yr
|
- | |
| 03 | 2.2442: Preheat combustion air with waste heat | $90,000 | $97,500 | - | - |
$90,000
-
MMBtu
|
|
| 04 | 2.4133: Use most efficient type of electric motors | $21,089 | $6,600 |
$12,737
219,600
kWh
|
$8,352
-
kW-mo/yr
|
- | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $12,710 | - |
$6,877
118,568
kWh
|
$5,833
-
kW-mo/yr
|
- | |
| 06 | 2.4227: Use compressor air filters | $4,048 | $2,400 |
$2,173
38,118
kWh
|
$1,875
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $148,477 | $149,820 |
$32,948
568,732
kWh
|
$25,529
-
kW-mo/yr
|
$90,000
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $114,678 | $143,220 |
$13,334
230,564
kWh
|
$11,344
-
kW-mo/yr
|
$90,000
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs