ITAC Assessment: MZ0091
ITAC logo
ITAC Assessment: MZ0091
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product electrical heaters
NAICS 335999: All Other Miscellaneous Electrical Equipment and Component Manufacturing
SIC 3699: Electrical Machinery, Equipment, and Supplies, Not Elsewhere
Sales Range less than $500
k
# of Employees 4
Plant Area 400,000
ft2
Annual Production 1
units
Production Hrs. Annual 4,368
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $354,959 3,770,053
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $269,456 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $269,456

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Primary Raw Material Savings
01 3.1191: Change procedures / equipment / operating conditions $190,000 $5,000 - - $190,000
02 2.8114: Change rate schedules or other changes in utility service $18,699 - - $18,699 -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $30,809 $27,800 $30,809
327,755
kWh
- -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,504 - $2,504
26,636
kWh
- -
05 3.1191: Change procedures / equipment / operating conditions $3,133 - $3,133
33,328
kWh
- -
06 3.4114: Replace city water with recycled water via cooling tower $24,311 $9,516 $(-888.6)
(-9,453)
kWh
$25,200 -
TOTAL RECOMMENDED $269,456 $42,316 $35,557
378,266
kWh
$43,899 $190,000
TOTAL IMPLEMENTED $269,456 $42,316 $35,557
378,266
kWh
$43,899 $190,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Fees Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs