| Assessment Year | 2012 |
|---|---|
| Principal Product | electrical heaters |
| NAICS | 335999: All Other Miscellaneous Electrical Equipment and Component Manufacturing |
| SIC | 3699: Electrical Machinery, Equipment, and Supplies, Not Elsewhere |
| Sales Range | less than $500 k |
| # of Employees | 4 |
| Plant Area |
400,000
ft2
|
| Annual Production | 1
units
|
| Production Hrs. Annual | 4,368
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $354,959 | 3,770,053 |
kWh
|
$0.094 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $269,456 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $269,456 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|
| 01 | 3.1191: Change procedures / equipment / operating conditions | $190,000 | $5,000 | - | - | $190,000 | |
| 02 | 2.8114: Change rate schedules or other changes in utility service | $18,699 | - | - | $18,699 | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $30,809 | $27,800 |
$30,809
327,755
kWh
|
- | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,504 | - |
$2,504
26,636
kWh
|
- | - | |
| 05 | 3.1191: Change procedures / equipment / operating conditions | $3,133 | - |
$3,133
33,328
kWh
|
- | - | |
| 06 | 3.4114: Replace city water with recycled water via cooling tower | $24,311 | $9,516 |
$(-888.6)
(-9,453)
kWh
|
$25,200 | - | |
| TOTAL RECOMMENDED | $269,456 | $42,316 |
$35,557
378,266
kWh
|
$43,899 | $190,000 | ||
| TOTAL IMPLEMENTED | $269,456 | $42,316 |
$35,557
378,266
kWh
|
$43,899 | $190,000 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Primary Raw Material Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs