Assessment Year | 2012 |
---|---|
Principal Product | tire retrading |
NAICS | 326212: Tire Retreading |
SIC | 7534: Tire Retreading and Repair Shops |
Sales Range | $50 M to 100M |
# of Employees | 250 |
Plant Area |
120,000
ft2
|
Annual Production | 10,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $72,450 | 572,605 |
kWh
|
$0.13 |
Electricity Demand | $8,345 | 3,129 |
kW-mo/yr
|
$2.67 |
Natural Gas | $192,894 | 27,756 |
MMBtu
|
$6.95 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $55,290 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $36,433 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,602 | $15,200 |
$5,391
44,928
kWh
|
$211
-
kW-mo/yr
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,756 | $3,500 |
$3,614
30,264
kWh
|
$142
-
kW-mo/yr
|
- | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,987 | $500 |
$2,987
24,892
kWh
|
- | - | |
04 | 2.2711: Utilize outside air instead of conditioned air for drying | $1,897 | $2,400 |
$1,897
15,810
kWh
|
- | - | |
05 | 2.7241: Install outside air damper / economizer on hvac unit | $12,831 | $37,520 | - | - |
$12,831
-
MMBtu
|
|
06 | 2.6212: Turn off equipment during breaks, reduce operating time | $7,736 | $11,730 |
$7,736
64,464
kWh
|
- | - | |
07 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $1,142 | $1,000 | - |
$1,142
-
kW-mo/yr
|
- | |
08 | 3.1161: Eliminate/reduce an operation | $6,939 | - | - | - |
$6,939
-
MMBtu
|
|
09 | 2.2511: Insulate bare equipment | $1,483 | $2,500 | - | - |
$1,483
-
MMBtu
|
|
10 | 2.1212: Operate boilers on high fire setting | $10,918 | $1,770 | - | - |
$10,918
-
MMBtu
|
|
TOTAL RECOMMENDED | $55,290 | $76,120 |
$21,624
180,358
kWh
|
$1,495
-
kW-mo/yr
|
$32,171
-
MMBtu
|
||
TOTAL IMPLEMENTED | $36,433 | $34,700 |
$16,740
139,656
kWh
|
$353
-
kW-mo/yr
|
$19,340
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs