Assessment Year | 2011 |
---|---|
Principal Product | Aluminum castings |
NAICS | 332710: Machine Shops |
SIC | 3334: Primary Production of Aluminum |
Sales Range | $10 M to 50M |
# of Employees | 109 |
Plant Area |
110,000
ft2
|
Annual Production | 10,000
pieces
|
Production Hrs. Annual | 5,760
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $92,160 | 1,728,000 |
kWh
|
$0.053 |
Electricity Demand | $127,583 | 10,115 |
kW-mo/yr
|
$12.61 |
Natural Gas | $45,106 | 5,111 |
MMBtu
|
$8.83 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $60,675 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $37,487 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7111: Reduce illumination to minimum necessary levels | $15,644 | $3,400 |
$10,462
197,395
kWh
|
$5,182
-
kW-mo/yr
|
- | |
02 | 2.7135: Install occupancy sensors | $285 | $610 |
$285
5,376
kWh
|
- | - | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $429 | - |
$429
8,087
kWh
|
- | - | |
04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $19,137 | $1,000 | - |
$19,137
-
kW-mo/yr
|
- | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,810 | $1,300 |
$7,810
97,552
kWh
|
- | - | |
06 | 2.4322: Use or replace with energy efficient substitutes | $7,545 | $1,133 |
$7,545
142,350
kWh
|
- | - | |
07 | 2.2437: Recover waste heat from equipment | $1,223 | $800 | - | - |
$1,223
-
MMBtu
|
|
08 | 2.6218: Turn off equipment when not in use | $35 | $50 | - | - |
$35
-
MMBtu
|
|
09 | 2.6218: Turn off equipment when not in use | $4,831 | - |
$4,831
91,156
kWh
|
- | - | |
10 | 2.4322: Use or replace with energy efficient substitutes | $3,736 | $6,494 |
$3,736
70,494
kWh
|
- | - | |
TOTAL RECOMMENDED | $60,675 | $14,787 |
$35,098
612,410
kWh
|
$24,319
-
kW-mo/yr
|
$1,258
-
MMBtu
|
||
TOTAL IMPLEMENTED | $37,487 | $10,254 |
$17,091
272,665
kWh
|
$19,137
-
kW-mo/yr
|
$1,258
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs