Assessment Year | 2011 |
---|---|
Principal Product | books |
NAICS | 323111: Commercial Printing (except Screen and Books) |
SIC | 2759: Commercial Printing, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 250 |
Plant Area |
1,200,000
ft2
|
Annual Production | 30,000,000
pieces
|
Production Hrs. Annual | 8,640
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $586,903 | 9,409,837 |
kWh
|
$0.062 |
Electricity Demand | $36,919 | 18,044 |
kW-mo/yr
|
$2.05 |
Natural Gas | $85,452 | 7,549 |
MMBtu
|
$11.32 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $535,189 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $158,643 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Primary Product Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4131: Size electric motors for peak operating efficiency | $1,000 | $10,000 |
$1,000
16,667
kWh
|
- | - | - | - | |
02 | 2.3212: Optimize plant power factor | $1,390 | $4,830 |
$1,390
22,100
kWh
|
- | - | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $87 | - |
$87
1,442
kWh
|
- | - | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,586 | $820 |
$5,586
88,723
kWh
|
- | - | - | - | |
05 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $13,830 | $1,000 | - |
$13,830
-
kW-mo/yr
|
- | - | - | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $326 | - |
$326
5,435
kWh
|
- | - | - | - | |
07 | 2.1233: Analyze flue gas for proper air/fuel ratio | $36,400 | - | - | - |
$36,400
-
MMBtu
|
- | - | |
08 | 2.7135: Install occupancy sensors | $630 | $250 |
$630
10,512
kWh
|
- | - | - | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $940 | $2,600 |
$890
13,804
kWh
|
$50
-
kW-mo/yr
|
- | - | - | |
10 | 2.8221: Consider intermediate or economy size autos / trucks | $65,000 | $85,000 | - | - | - | $65,000 | - | |
11 | 4.322: Eliminate old stock and modify inventory control | $120,000 | $150,000 | - | - | - | $120,000 | - | |
12 | 3.1163: Use plastic pallets instead of wood | $25,000 | $5,000 | - | - | - | - | $25,000 | |
13 | 4.122: Develop standard procedures to improve internal yields | $35,000 | $8,500 | - | - | - | $35,000 | - | |
14 | 4.122: Develop standard procedures to improve internal yields | $115,000 | $12,500 | - | - | - | $115,000 | - | |
15 | 4.122: Develop standard procedures to improve internal yields | $115,000 | $125,000 | - | - | - | $115,000 | - | |
TOTAL RECOMMENDED | $535,189 | $405,500 |
$9,909
158,683
kWh
|
$13,880
-
kW-mo/yr
|
$36,400
-
MMBtu
|
$450,000 | $25,000 | ||
TOTAL IMPLEMENTED | $158,643 | $128,670 |
$7,193
114,481
kWh
|
$50
-
kW-mo/yr
|
$36,400
-
MMBtu
|
$115,000 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Primary Product Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs