Assessment Year | 2008 |
---|---|
Principal Product | Fabricated metal sheet products |
NAICS | 332322: Sheet Metal Work Manufacturing |
SIC | 3444: Sheet Metal Work |
Sales Range | $10 M to 50M |
# of Employees | 92 |
Plant Area |
100,000
ft2
|
Annual Production | 300,000
pieces
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $135,397 | 2,315,100 |
kWh
|
$0.058 |
Natural Gas | $186,649 | 24,894 |
MMBtu
|
$7.50 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $55,068 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $55,068 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.1122: Re-size charging openings or add a movable door on equipment | $1,425 | $2,800 | - |
$1,425
-
MMBtu
|
|
02 | 2.4221: Install compressor air intakes in coolest locations | $382 | $900 |
$382
7,764
kWh
|
- | |
03 | 2.2223: Enhance sensitivity of temperature control and cutoff | $11,853 | $5,458 | - |
$11,853
-
MMBtu
|
|
04 | 3.1161: Eliminate/reduce an operation | $41,408 | - | - |
$41,408
-
MMBtu
|
|
TOTAL RECOMMENDED | $55,068 | $9,158 |
$382
7,764
kWh
|
$54,686
-
MMBtu
|
||
TOTAL IMPLEMENTED | $55,068 | $9,158 |
$382
7,764
kWh
|
$54,686
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs