Assessment Year | 2007 |
---|---|
Principal Product | Electric transformer core |
NAICS | 335311: Power, Distribution, and Specialty Transformer Manufacturing |
SIC | 3612: Power, Distribution, and Specialty Transformers |
Sales Range | $10 M to 50M |
# of Employees | 60 |
Plant Area |
25,000
ft2
|
Annual Production | 60,000
pieces
|
Production Hrs. Annual | 4,680
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $42,087 | 484,898 |
kWh
|
$0.087 |
Natural Gas | $58,090 | 4,293 |
MMBtu
|
$13.53 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $48,665 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Gaseous Waste Savings |
---|---|---|---|---|---|---|---|
01 | 4.111: Add equipment/ operators to reduce production bottleneck | $25,600 | - |
$20,700
308,880
kWh
|
$4,900
-
kW-mo/yr
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,872 | - |
$10,438
153,504
kWh
|
$2,434
-
kW-mo/yr
|
- | |
03 | 2.7135: Install occupancy sensors | $3,576 | $2,450 |
$3,576
61,660
kWh
|
- | - | |
04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $1,001 | $2,500 | - |
$1,001
-
kW-mo/yr
|
- | |
05 | 2.5194: Redesign process | $5,616 | - | - | - |
$5,616
-
lb
|
|
TOTAL RECOMMENDED | $48,665 | $4,950 |
$34,714
524,044
kWh
|
$8,335
-
kW-mo/yr
|
$5,616
-
lb
|
||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs