ITAC Assessment: MZ0015
ITAC logo
ITAC Assessment: MZ0015
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2007
Principal Product Fabric filter media for air emissions
NAICS 313310: Textile and Fabric Finishing Mills
SIC 2297: Non-woven Fabrics
Sales Range $5
M
to 10
M
# of Employees 200
Plant Area 120,000
ft2
Annual Production 1
units
Production Hrs. Annual 4,400
hrs
Location (State) Missouri

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $103,653 1,671,560
kWh
Natural Gas $48,077 4,401
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $17,275 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,166

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4221: Install compressor air intakes in coolest locations $1,790 $900 $1,790
33,941
kWh
-
02 2.7135: Install occupancy sensors $376 $180 $376
9,400
kWh
-
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $15,109 - - $15,109
-
kW-mo/yr
TOTAL RECOMMENDED $17,275 $1,080 $2,166
43,341
kWh
$15,109
-
kW-mo/yr
TOTAL IMPLEMENTED $2,166 $1,080 $2,166
43,341
kWh
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs