Assessment Year | 2007 |
---|---|
Principal Product | oil coolers, water cooler, exhaust gas recooler, charge air cooler |
NAICS | 332410: Power Boiler and Heat Exchanger Manufacturing |
SIC | 3443: Fabricated Plate Work (Boiler Shops) |
Sales Range | $5 M to 10M |
# of Employees | 178 |
Plant Area |
35,000
ft2
|
Annual Production | 1
units
|
Production Hrs. Annual | 6,324
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $650,000 | 8,877,336 |
kWh
|
$0.073 |
Natural Gas | $165,000 | 16,915 |
MMBtu
|
$9.75 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $130,781 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,922 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $5,138 | $2,230 | - | - |
$5,138
-
MMBtu
|
|
02 | 2.2136: Install / repair insulation on steam lines | $18,457 | $3,412 | - | - |
$18,457
-
MMBtu
|
|
03 | 2.4221: Install compressor air intakes in coolest locations | $5,707 | $1,300 |
$5,707
63,452
kWh
|
- | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $184 | $150 |
$184
2,556
kWh
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,950 | $24,700 |
$13,950
202,356
kWh
|
- | - | |
06 | 2.7122: Disconnect ballasts | $19,720 | $1,050 |
$19,720
279,444
kWh
|
- | - | |
07 | 2.7135: Install occupancy sensors | $6,900 | $2,950 |
$6,900
131,400
kWh
|
- | - | |
08 | 2.6222: Use drying oven (batch type) on alternate days or other optimum schedule to run equipment with full loads | $56,125 | - | - |
$56,125
-
kW-mo/yr
|
- | |
09 | 2.7124: Make a practice of turning off lights when not needed | $4,600 | - |
$4,600
87,600
kWh
|
- | - | |
TOTAL RECOMMENDED | $130,781 | $35,792 |
$51,061
766,808
kWh
|
$56,125
-
kW-mo/yr
|
$23,595
-
MMBtu
|
||
TOTAL IMPLEMENTED | $9,922 | $2,380 |
$4,784
90,156
kWh
|
- |
$5,138
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs