Assessment Year | 2007 |
---|---|
Principal Product | Radiators |
NAICS | 336390: Other Motor Vehicle Parts Manufacturing |
SIC | 3363: Aluminum Die-Castings |
Sales Range | $10 M to 50M |
# of Employees | 270 |
Plant Area |
150,000
ft2
|
Annual Production | 11,000
units
|
Production Hrs. Annual | 3,952
hrs
|
Location (State) | Missouri |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Demand | $422,021 | 8,907,800 |
kW-mo/yr
|
$0.047 |
Natural Gas | $559,693 | 53,656 |
MMBtu
|
$10.43 |
Fuel Oil #1 | $5,000 | 517 |
MMBtu
|
$9.67 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $131,672 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $82,315 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $25,357 | $20,580 |
$25,357
147
kWh
|
- | |
02 | 2.112: Hardware | $75,000 | $78,000 | - |
$75,000
-
MMBtu
|
|
03 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $3,400 | $800 | - |
$3,400
-
MMBtu
|
|
04 | 2.112: Hardware | $24,000 | $78,000 | - |
$24,000
-
MMBtu
|
|
05 | 2.2136: Install / repair insulation on steam lines | $3,915 | $3,300 | - |
$3,915
-
MMBtu
|
|
TOTAL RECOMMENDED | $131,672 | $180,680 |
$25,357
147
kWh
|
$106,315
-
MMBtu
|
||
TOTAL IMPLEMENTED | $82,315 | $82,100 | - |
$82,315
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs