Assessment Year | 2022 |
---|---|
Principal Product | Auto Parts |
NAICS | 541380: Testing Laboratories |
SIC | 8711: Engineering Services |
Sales Range | less than $500 k |
# of Employees | 140 |
Plant Area |
50,000
ft2
|
Annual Production | 1
pieces
|
Production Hrs. Annual | 2,600
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $23,570 | 1,148,000 |
kWh
|
$0.021 | |
Electricity Demand | $119,361 | 2,813 |
kW-mo/yr
|
$42.43 | |
Electricity Fees | $5,652 | - |
|
- | |
Natural Gas | $9,575 | 1,227 |
MMBtu
|
$7.80 | |
Waste Disposal Costs | |||||
Water Usage | $10,090 | 777 |
Tgal
|
$12.99 | |
TOTAL YEARLY COSTS | $168,248 | ||||
RECOMMENDED SAVINGS* | $4,722 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Usage Savings |
---|---|---|---|---|---|---|---|
01 | 2.7111: Reduce illumination to minimum necessary levels | $1,473 | $3,866 |
$502
16,726
kWh
|
$972
-
kW-mo/yr
|
- | |
02 | 2.7135: Install occupancy sensors | $693 | $1,199 |
$236
7,859
kWh
|
$457
-
kW-mo/yr
|
- | |
03 | 3.4151: Minimize water usage | $2,556 | $11,427 | - | - |
$2,556
-
Tgal
|
|
TOTAL RECOMMENDED | $4,722 | $16,492 |
$738
24,585
kWh
|
$1,429
-
kW-mo/yr
|
$2,556
-
Tgal
|
||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs