| Assessment Year | 2026 |
|---|---|
| Principal Product | Automotive interior components and injection-molded plastic parts |
| NAICS | 326199: All Other Plastics Product Manufacturing |
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $100 M to 500M |
| # of Employees | 481 |
| Plant Area |
315,000
ft2
|
| Annual Production | 10,000,000
units
|
| Production Hrs. Annual | 5,824
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $992,243 | 17,633,673 |
kWh
|
$0.056 | |
| Electricity Demand | $302,610 | 12,960 |
kW-mo/yr
|
$23.35 | |
| Electricity Fees | $78,615 | - |
|
- | |
| Natural Gas | $43,867 | 9,096 |
MMBtu
|
$4.82 | |
| Waste Disposal Costs | |||||
| Water Usage | $6,615 | 750 |
Tgal
|
$8.82 | |
| TOTAL YEARLY COSTS | $1,423,950 | ||||
| RECOMMENDED SAVINGS* | $152,358 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.9114: Use solar heat to make electricty | $58,514 | $898,400 |
$31,476
562,067
kWh
|
$27,038
-
kW-mo/yr
|
- | - | |
| 02 | 2.1321: Replace fossil fuel equipment with electrical equipment | $27,468 | - |
$4,013
(-71,668)
kWh
|
$9,190
-
kW-mo/yr
|
$14,265
-
MMBtu
|
- | |
| 03 | 4.454: Modify startup/shutdown times | $31,815 | - |
$17,135
305,976
kWh
|
$14,680
-
kW-mo/yr
|
- | - | |
| 04 | 2.3212: Optimize plant power factor | $12,469 | $38,117 | - | - | - | $12,469 | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $10,362 | - |
$5,573
99,525
kWh
|
$4,789
-
kW-mo/yr
|
- | - | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,092 | $180 |
$587
10,489
kWh
|
$504
-
kW-mo/yr
|
- | - | |
| 07 | 2.7111: Reduce illumination to minimum necessary levels | $891 | - |
$480
8,561
kWh
|
$411
-
kW-mo/yr
|
- | - | |
| 08 | 2.7135: Install occupancy sensors | $243 | $1,260 |
$117
2,079
kWh
|
$126
-
kW-mo/yr
|
- | - | |
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $183 | $867 |
$116
2,085
kWh
|
$68
-
kW-mo/yr
|
- | - | |
| 10 | 2.7221: Lower temperature during the winter season and vice-versa | $2,320 | - |
$667
11,909
kWh
|
$1,215
-
kW-mo/yr
|
$438
-
MMBtu
|
- | |
| 11 | 2.7261: Install timers and/or thermostats | $233 | $520 | - | - |
$233
-
MMBtu
|
- | |
| 12 | 4.821: Pay bills on time to avoid late fees | $6,768 | - | - | - | - | $6,768 | |
| TOTAL RECOMMENDED | $152,358 | $939,344 |
$60,164
931,023
kWh
|
$58,021
-
kW-mo/yr
|
$14,936
-
MMBtu
|
$19,237 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs