ITAC Assessment: MU0074
ITAC logo
ITAC Assessment: MU0074
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Silicone Products
NAICS 325199: All Other Basic Organic Chemical Manufacturing
SIC 2899: Chemicals and Chemical Preparations, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 90
Plant Area 110,000
ft2
Annual Production 6,614
ton
Production Hrs. Annual 6,240
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $135,872 1,190,860
kWh
Electricity Demand $40,811 3,418
kW-mo/yr
Electricity Fees $6,749 -
Natural Gas $48,829 8,587
MMBtu
Other Gas $3,883 1
MMBtu
Waste Disposal Costs
Water Usage $25,031 2
Tgal
TOTAL YEARLY COSTS $261,175
RECOMMENDED SAVINGS* $30,900 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 2.9114: Use solar heat to make electricty $20,533 $184,800 $20,533
180,111
kWh
- - -
02 2.8121: Apply for tax-free status for energy purchases $6,046 - - - - $6,046
03 2.1321: Replace fossil fuel equipment with electrical equipment $729 $7,330 - - - $729
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $65 $140 $54
491
kWh
$11
-
kW-mo/yr
- -
05 2.7111: Reduce illumination to minimum necessary levels $2,223 - $1,802
16,384
kWh
$421
-
kW-mo/yr
- -
06 2.7135: Install occupancy sensors $68 $404 $46
415
kWh
$23
-
kW-mo/yr
- -
07 2.7221: Lower temperature during the winter season and vice-versa $1,235 $166 $610
5,354
kWh
$373
-
kW-mo/yr
$252
-
MMBtu
-
TOTAL RECOMMENDED $30,900 $192,840 $23,045
202,755
kWh
$828
-
kW-mo/yr
$252
-
MMBtu
$6,775
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs