ITAC Assessment: MU0059
ITAC logo
ITAC Assessment: MU0059
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Heavy machinery trucks
NAICS 333318: Other Commercial and Service Industry Machinery Manufacturing
SIC 3537: Industrial Trucks, Tractors, Trailers, and Stackers
Sales Range $10
M
to 50
M
# of Employees 66
Plant Area 75,000
ft2
Annual Production 200
units
Production Hrs. Annual 2,184
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $28,926 224,560
kWh
Electricity Fees $4,981 -
Natural Gas $29,054 4,386
MMBtu
Other Energy $6,204 1
MMBtu
Waste Disposal Costs
Water Usage $2,576 99
Tgal
TOTAL YEARLY COSTS $71,741
RECOMMENDED SAVINGS* $22,829 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Other Energy Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,763 $403 $1,763
13,580
kWh
- -
02 2.4322: Use or replace with energy efficient substitutes $105 $600 $105
809
kWh
- -
03 2.4322: Use or replace with energy efficient substitutes $4,093 $1,951 $(-280.4)
(-2,157)
kWh
$3,088
-
MMBtu
$1,285
-
MMBtu
04 2.4322: Use or replace with energy efficient substitutes $814 $2,920 - $814
-
MMBtu
-
05 2.7111: Reduce illumination to minimum necessary levels $2,373 - $2,373
18,252
kWh
- -
06 2.7135: Install occupancy sensors $960 $2,327 $960
7,390
kWh
- -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $778 $487 $778
5,984
kWh
- -
08 2.7491: Insulate glazing, walls, ceilings, and roofs $2,664 $1,940 - $2,664
-
MMBtu
-
09 2.9114: Use solar heat to make electricty $9,279 $76,908 $9,279
71,375
kWh
- -
TOTAL RECOMMENDED $22,829 $87,536 $14,978
115,233
kWh
$6,567
-
MMBtu
$1,285
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Other Energy Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs