| Assessment Year | 2024 |
|---|---|
| Principal Product | Brass/Copper fittings |
| NAICS | 332721: Precision Turned Product Manufacturing |
| SIC | 3451: Screw Machine Products |
| Sales Range | $100 M to 500M |
| # of Employees | 350 |
| Plant Area |
190,000
ft2
|
| Annual Production | 6,000,000
units
|
| Production Hrs. Annual | 7,488
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $593,543 | 10,349,893 |
kWh
|
$0.057 |
| Electricity Demand | $123,287 | 25,632 |
kW-mo/yr
|
$4.81 |
| Electricity Fees | $30,758 | - |
|
- |
| Natural Gas | $48,987 | 8,220 |
MMBtu
|
$5.96 |
| Other Gas | $465 | 1 |
MMBtu
|
$465.23 |
| TOTAL YEARLY COSTS | $797,040 | |||
| RECOMMENDED SAVINGS* | $25,870 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2211: Use optimum temperature | $6,955 | - |
$5,577
92,949
kWh
|
$717
-
kW-mo/yr
|
$662
-
MMBtu
|
|
| 02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $8,402 | $28,100 |
$7,445
124,085
kWh
|
$957
-
kW-mo/yr
|
- | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $6,874 | - |
$6,091
101,524
kWh
|
$783
-
kW-mo/yr
|
- | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,876 | $1,801 |
$1,662
27,705
kWh
|
$214
-
kW-mo/yr
|
- | |
| 05 | 2.7135: Install occupancy sensors | $1,296 | - |
$1,148
19,139
kWh
|
$148
-
kW-mo/yr
|
- | |
| 06 | 2.7492: Use proper thickness of insulation on building envelope | $118 | $272 |
$18
296
kWh
|
$2
-
kW-mo/yr
|
$98
-
MMBtu
|
|
| 07 | 2.7496: Install partitions to reduce size of conditioned space | $349 | - | - | - |
$349
-
MMBtu
|
|
| TOTAL RECOMMENDED | $25,870 | $30,173 |
$21,942
365,697
kWh
|
$2,819
-
kW-mo/yr
|
$1,109
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs