Assessment Year | 2024 |
---|---|
Principal Product | Gas Tanks |
NAICS | 336320: Motor Vehicle Electrical and Electronic Equipment Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $50 M to 100M |
# of Employees | 161 |
Plant Area |
160,000
ft2
|
Annual Production | 500,000
units
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $772,074 | 15,944,822 |
kWh
|
$0.048 | |
Electricity Demand | $149,215 | 35,265 |
kW-mo/yr
|
$4.23 | |
Electricity Fees | $42,133 | - |
|
- | |
Natural Gas | $51,428 | 10,650 |
MMBtu
|
$4.83 | |
Waste Disposal Costs | |||||
Water Usage | $19,325 | 2,829,684 |
Tgal
|
$0.007 | |
Water Disposal | $109,364 | 2,825,574 |
Tgal
|
$0.039 | |
TOTAL YEARLY COSTS | $1,143,539 | ||||
RECOMMENDED SAVINGS* | $182,130 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $5,217 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Usage Savings | Water Disposal Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4322: Use or replace with energy efficient substitutes | $106,121 | $1,404,000 |
$104,640
2,180,000
kWh
|
$1,481
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.7135: Install occupancy sensors | $213 | $315 |
$190
3,954
kWh
|
$23
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,004 | $41 |
$4,901
102,111
kWh
|
$103
-
kW-mo/yr
|
- | - | - | - | |
04 | 3.4151: Minimize water usage | $68,486 | $150,124 | - | - | - |
$7,317
-
Tgal
|
$40,766
-
Tgal
|
$20,403 | |
05 | 4.821: Pay bills on time to avoid late fees | $2,306 | - | - | - | $2,306 | - | - | - | |
TOTAL RECOMMENDED | $182,130 | $1,554,480 |
$109,731
2,286,065
kWh
|
$1,606
-
kW-mo/yr
|
$2,306 |
$7,317
-
Tgal
|
$40,766
-
Tgal
|
$20,403 | ||
TOTAL IMPLEMENTED | $5,217 | $356 |
$5,091
106,065
kWh
|
$126
-
kW-mo/yr
|
- | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs